Iterations

Version history

Iterations are a way to track issues over a period of time. This allows teams to track velocity and volatility metrics. For tracking over different time periods, you can use iterations milestones. You can create and manage various iteration cadences.

For example, you can use:

  • Milestones for Program Increments, which span 8-12 weeks.
  • Iterations for Sprints, which span 2 weeks.

In GitLab, iterations are similar to milestones, with a few differences:

  • Iterations are only available to groups.
  • Iterations are grouped into iteration cadences.
  • Iterations require both a start and an end date.
  • Iteration date ranges cannot overlap within an iteration cadence.

Iteration cadences

Version history
  • Introduced in GitLab 14.1 with a flag, named iteration_cadences. Disabled by default.
  • Changed in GitLab 15.0: All scheduled iterations must start on the same day of the week as the cadence start day. Start date of cadence cannot be edited after the first iteration starts.
  • Enabled on GitLab.com and self-managed in GitLab 15.0.
  • Changed in GitLab 15.4: A new automation start date can be selected for cadence. Upcoming iterations are scheduled to start on the same day of the week as the changed start date. Iteration cadences can be manually managed by turning off the automatic scheduling feature.
  • Generally available in GitLab 15.5. Feature flag iteration_cadences removed.

Iteration cadences are containers for iterations and can be used to automate iteration scheduling. You can use them to automate creating iterations every 1, 2, 3, or 4 weeks. You can also configure iteration cadences to automatically roll over incomplete issues to the next iteration.

Create an iteration cadence

Changed the minimum user role from Developer to Reporter in GitLab 15.0.

Prerequisites:

  • You must have at least the Reporter role for a group.

To create an iteration cadence:

  1. On the top bar, select Main menu > Groups and find your group.
  2. On the left sidebar, select Issues > Iterations.
  3. Select New iteration cadence.
  4. Enter the title and description of the iteration cadence.
  5. To manually manage the iteration cadence, clear the Enable automatic scheduling checkbox and skip the next step.
  6. Complete the required fields to use automatic scheduling.
    • Select the automation start date of the iteration cadence. Iterations are scheduled to begin on the same day of the week as the day of the week of the start date.
    • From the Duration dropdown list, select how many weeks each iteration should last.
    • From the Upcoming iterations dropdown list, select how many upcoming iterations should be created and maintained by GitLab.
    • Optional. To move incomplete issues to the next iteration, select Roll over issues.
  7. Select Create cadence. The cadence list page opens.

If you want to manually manage the created cadence, read Manual Iteration Management.

View the iterations list

  1. On the top bar, select Main menu > Groups and find your group.
  2. Select Issues > Iterations.

To view all the iterations in a cadence, ordered by descending date, select that iteration cadence. From there you can create a new iteration or select an iteration to get a more detailed view.

note
If a project has issue tracking turned off, to view the iterations list, enter its URL. To do so, add: /-/cadences to your project or group URL. For example https://gitlab.com/gitlab-org/sample-data-templates/sample-gitlab-project/-/cadences. This is tracked in issue 339009.

Edit an iteration cadence

Prerequisites:

  • You must have at least the Developer role for a group.

To edit an iteration cadence:

  1. On the top bar, select Main menu > Groups and find your group.
  2. On the left sidebar, select Issues > Iterations.
  3. Select Edit iteration cadence.

When you use automatic scheduling and edit the Automation start date field, you must set a new start date that doesn’t overlap with the existing current or past iterations.

Editing Upcoming iterations is a non-destructive action. If ten upcoming iterations already exist, changing the number under Upcoming iterations to 2 doesn’t delete the eight existing upcoming iterations.

Turn on and off automatic scheduling for an iteration cadence

  1. On the top bar, select Main menu > Groups and find your group.
  2. On the left sidebar, select Issues > Iterations.
  3. Next to the cadence for which you want to turn on or off automatic scheduling, select the three-dot menu () > Edit cadence.
  4. Select or clear the Enable automatic scheduling checkbox.
  5. If you’re turning on automatic scheduling, complete the required fields Duration, Upcoming iterations, and Automation start date.

    For Automation start date, you can select any date that doesn’t overlap with the existing open iterations. If you have upcoming iterations, the automatic scheduling adjusts them appropriately to fit your chosen duration.

  6. Select Save changes.

Example of turning on automatic scheduling for a manual iteration cadence

Suppose it’s Friday, April 15, and you have three iteration in a manual iteration cadence:

  • Monday, April 4 - Friday, April 8 (closed)
  • Tuesday, April 12 - Friday, April 15 (ongoing)
  • Tuesday, May 3 - Friday, May 6 (upcoming)

The earliest possible Automation start date you can choose is Saturday, April 16 in this scenario, because April 15 overlaps with the ongoing iteration.

If you select Monday, April 18 as the automation start date to automate scheduling iterations every week up to two upcoming iterations, after the conversion you have the following iterations:

  • Monday, April 4 - Friday, April 8 (closed)
  • Tuesday, April 12 - Friday, April 15 (ongoing)
  • Monday, April 18 - Sunday, April 24 (upcoming)
  • Monday, April 25 - Sunday, May 1 (upcoming)

Your existing upcoming iteration “Tuesday, April 12 - Friday, April 15” is changed to “April 18 - Sunday, April 24”.

An additional upcoming iteration “April 25 - Sunday, May 1” is scheduled to satisfy the requirement that there are at least two upcoming iterations scheduled.

Delete an iteration cadence

Changed the minimum user role from Developer to Reporter in GitLab 15.0.

Prerequisites:

  • You must have at least the Reporter role for a group.

Deleting an iteration cadence also deletes all iterations within that cadence.

To delete an iteration cadence:

  1. On the top bar, select Main menu > Groups and find your group.
  2. On the left sidebar, select Issues > Iterations.
  3. Select the three-dot menu () > Delete cadence for the cadence you want to delete.
  4. Select Delete cadence.

Manual iteration management

If you don’t want your iterations to be scheduled by iteration cadences, you can also create and manage them manually.

Create an iteration

Changed the minimum user role from Developer to Reporter in GitLab 15.0.

Prerequisites:

To create an iteration:

  1. On the top bar, select Main menu > Groups and find your group.
  2. On the left sidebar, select Issues > Iterations and select an iteration cadence.
  3. Select New iteration.
  4. Enter the title, a description (optional), a start date, and a due date.
  5. Select Create iteration. The iteration details page opens.

Edit an iteration

Version history
  • Introduced in GitLab 13.2.
  • Changed the minimum user role from Developer to Reporter in GitLab 15.0.

Prerequisites:

To edit an iteration, select the three-dot menu () > Edit.

Delete an iteration

Version history
  • Introduced in GitLab 14.3.
  • Changed the minimum user role from Developer to Reporter in GitLab 15.0.

Prerequisites:

To delete an iteration, select the three-dot menu () > Delete.

Add an issue to an iteration

Introduced in GitLab 13.2.

To learn how to add an issue to an iteration, see the steps in Managing issues.

View an iteration report

Viewing iteration reports in projects introduced in GitLab 13.5.

You can track the progress of an iteration by reviewing iteration reports. An iteration report displays a list of all the issues assigned to an iteration and their status.

The report also shows a breakdown of total issues in an iteration. Open iteration reports show a summary of completed, unstarted, and in-progress issues. Closed iteration reports show the total number of issues completed by the due date.

To view an iteration report, go to the iterations list page and select an iteration’s period.

Iteration burndown and burnup charts

Version history

The iteration report includes burndown and burnup charts, similar to how they appear when viewing a milestone.

Burndown charts help track completion progress of total scope, and burnup charts track the daily total count and weight of issues added to and completed in a given timebox.

Iteration charts scoped to subgroups or projects

Introduced in GitLab 14.9.

You can view burndown and burnup charts for iterations created for a group in any of its subgroups or projects. When you do this, the charts only count the issues that belong to the subgroup or project.

For example, suppose a group has two projects named Project 1 and Project 2. Each project has a single issue assigned to the same iteration from the group.

An iteration report generated for the group shows issue counts for all the group’s projects:

  • Completed: 0 of 2
  • Incomplete: 0 of 2
  • Unstarted: 2 of 2
  • Burndown chart total issues: 2
  • Burnup chart total issues: 2

An iteration report generated for Project 1 shows only issues that belong to this project:

  • Completed: 0 of 1
  • Incomplete: 0 of 1
  • Unstarted: 1 of 1
  • Burndown chart total issues: 1
  • Burnup chart total issues: 1

Group issues by label

Introduced in GitLab 13.8.

You can group the list of issues by label. This can help you view issues that have your team’s label, and get a more accurate understanding of scope attributable to each label.

To group issues by label:

  1. On the top bar, select Main menu > Groups and find your group.
  2. On the left sidebar, select Issues > Iterations.
  3. In the Group by dropdown list, select Label.
  4. Select the Filter by label dropdown list.
  5. Select the labels you want to group by in the labels dropdown list. You can also search for labels by typing in the search input.
  6. Select any area outside the label dropdown list. The page is now grouped by the selected labels.